Ensuring the transmission of excess electricity produced from renewable energy sources via a power plant to the electricity supply network for compensation purposes, as well as the ability to receive electricity from the network when consumption exceeds production. 

List of required documents: 
Subscriber's identity card;
Subscriber code;
Existing technical specifications obtained from the power supply network;
Project documents reflecting the technical characteristics of the active consumer's power plant (rooftop solar panels, wind power plant, etc.), and a certificate of completion for the technical installation works.

Forms of implementation:
  • Applying without visiting the service center and electronic delivery of the result
  • Applying by visiting the service center and delivery of the result in paper form
  • Organization of mobile service based on the citizen's request


Information about the service user:
  • Individuals
  • Legal entities



Electronic address: