S/S Region name Date Break time Name of the work Areas
8251 Xətai 2024-07-26 09:00-14:00 TM 604 inspection K.Ahmadov street courtyard houses
8252 Xətai 2024-07-23 09:00-14:00 TM 605 inspection Building No. 24, Y. Safarov Street, courtyard houses
8253 Xətai 2024-07-19 09:00-14:00 TM 895 inspection Buildings No. 39 A, B and 47 A, B, G. A. Shikhlinski Street, Pumping station
8254 Xətai 2024-07-16 09:00-14:00 TM 224 inspection Buildings No. 57, 59 G.A. Shikhlinski Street, 98, 100 G.S. Mehmandarov Street, Poliklenika No. 8, MIS 96
8255 Xətai 2024-07-12 09:00-14:00 TM 223 inspection Buildings No. 90, 92, 94 and 96, G.S. Mehmandarov Street, Kindergarten No. 241
8256 Xətai 2024-07-09 09:00-14:00 TM 222 inspection Buildings No. 49, 51 G.A. Shikhlinski Street, 80, 82, 84, 96 G.S. Mehmandarov Street, School No. 24, ATS 579
8257 Xətai 2024-07-05 09:00-14:00 TM 221 inspection Buildings No. 1, 2, 3A, 37 and 39, School No. 263, Kindergartens No. 237 and 249, G. A. Shikhlinski Street
8258 Xətai 2024-07-02 09:00-14:00 TM 220 inspection Buildings No. 66, 68, 70, 72, 74 and 76, G.S. Mehmandarov Street, Pumping Station, Heating Station
8259 Biləcəri 2024-08-26 09:00:17 KTM-78/1 new power plant Sulutepa area
8260 Biləcəri 2024-08-22 09:00:17 KTM-607/1 new power plant Village Bimaqadi area
8261 Biləcəri 2024-08-12 09:00:17 KTM-283/1 new power plant Sulutepa area
8262 Biləcəri 2024-08-08 09:00:17 KTM-235/1 new power plant Sulutepa area
8263 Biləcəri 2024-08-06 09:00:17 KTM-343/1 new power plant DSK road
8264 Biləcəri 2024-08-02 09:00:17 KTM-31 power boost DYP upper part
8265 Biləcəri 2024-08-01 09:00:17 Drawing a new feeder KTM-99 DSK road
8266 Biləcəri 2024-07-31 09:00:17 Drawing a new feeder KTM-256 DSK road
8267 Biləcəri 2024-07-30 09:00:12 Drawing a new feeder KTM-31 DYP upper part
8268 Biləcəri 2024-07-29 09:00:15 Drawing a new feeder KTM-234 Subsection of DYP
8269 Biləcəri 26.07.2024 09:00-12:00 Drawing a new feeder KTM-253 Malik Aslanov Street
8270 Biləcəri 25.07.2024 09:00-12:00 Drawing a new feeder KTM-30 Asaf Zeynalli
8271 Biləcəri 24.07.2024 09:00-12:00 TM-843 drawing a new feeder A brand new array
8272 Biləcəri 23.07.2024 09:00-12:00 Drawing a new feeder KTM-252 A brand new array
8273 Biləcəri 22.07.2024 09:00-12:00 Laying of TM-3 new feeders Mehdi Huseyn Street
8274 Biləcəri 19.07.2024 09:00-17:00 Power increase in KTM 1456 A brand new array
8275 Bağlar 05-09.08.2024 4-5 hours Inspection of 6 kV TDX-Novkhani line, replacement of corroded wires, transfer of 9 power transformers from 6 kV Novkhani-3 line to TDX-Novkhani line Sarigaya and a part of Novkhani village
8276 Bağlar 22.07-09.08.2024 4-5 hours Removal of loads from overloaded 6 kV Novkhani-1 line and transfer to 6 kV Novkhani-3 line Part of Novkhani village
8277 Bağlar 22-24.07.2024 3-4 hours Inspection of the connection points of the XLPE-10 type cables to the balance KTMs fed from the 6 kV ETI line A part of Goredil village
8278 Bağlar 29-31.07.2024 2-3 hours Replacement of corroded wires, damaged insulators, pruning of the green mass under the line on the 6 kV Communication-1 line Part of Fatmayi gardens
8279 Bağlar 19-23.08.2024 4-5 hours Replacement of corroded wires and damaged insulators on the 6 kV Ministry of Communications line, pruning of the green mass under the line, trimming of the line Fatmayi gardens
8280 Bağlar 12-16.08.2024 3-4 hours Inspection of the connection points of the XLPE-10 type cables falling into the balance KTMs fed from the 10 kV Mahammadi-3 line Mammadli village
8281 Bağlar 29.07-02.08.2024 4-5 hours Inspection of clamps on 6 kV Mehdiabad-1 line Mehdiabad settlement
8282 Bağlar 22-26.07.2024 4-5 hours 6 kV RP16-Digah line replacement of corroded wires, damaged insulators, pruning of green mass under the line Digah settlement
8283 Bağlar 16-19.07.2024 3-4 hours Replacement of corroded wires, damaged insulators, pruning of the green mass under the line on the 6 kV Mehdiabad-2 line Mehdiabad settlement