S/S Region name Date Break time Name of the work Areas
7801 Masallı 2024.11.4 2 hours 110/35/10 square meters of Masalli y/st of 10 square meters No. 7 Garibler h/x, pruning of the green mass below the 0.4 square meter line, pruning of lines Gariblar, Mammadrazakuche, Dambalov, Isi, Shikhlar, Godman Azizabad villages
7802 Masallı 2024.11.4 2 hours 110/35/10 sq.m. in the 10 sq.m. No. 10 Kizylagac h/x from Masalli y/st, replacement of unusable wires, pruning of the green mass under the line, trimming of wires Kizylagac, Huseynhajili, Musakücha and Vilash villages
7803 Biləsuvar 2024.11.1-10 3-4 hours Current repair work at 10 kV h/x No. 4 Urban area
7804 Biləsuvar 2024.11.1-30 3-4 hours In connection with the reconstruction works at the 10 kV substation No. 6. Asgarabad village and Ashagi-Jurali village.
7805 Biləsuvar 2024.11.4 3-4 hours Pruning works and replacement of defective 10 kV insulators in 10 kV h/x No. 9. Bagbanlar village and Zahmadabad village
7806 Biləsuvar 2024.11.1 3-4 hours Trimming and replacement of defective 10 kV insulators at 10 kV h/x No. 7 Khirmandali village area
7807 Biləsuvar 2024.11.1-2 3-4 hours In connection with pruning works at the 10 kV h/x No. 1 Urban area
7808 Biləsuvar 2024.11.1-20 2-3 hours In connection with the works of reconstruction of 10 kV substation No. 1 Mughan village and Yukhari-Agalikand village
7809 Biləsuvar 2024.11.1-30 2-3 hours Demolition of the old line in the area where reconstruction works of 10 kV substation No. 4 have been completed Aghalikand area
7810 Biləsuvar 2024.11.1-30 3-4 hours In connection with the reconstruction works of the 10 kV substation No. 8 Ismetli, Guneshli and Aghayri villages
7811 Astara 2024.11.29 2 hours Replacement of exposed wires and damaged insulators in the 10 kV Erchivan farm overhead line, pruning of the green mass under the line, pruning of the line Erchivan settlement
7812 Astara 2024.11.15 1 hour Replacement of exposed wires and damaged insulators in the 10 kV Erchivan farm overhead line, pruning of the green mass under the line, pruning of the line Erchivan settlement
7813 Astara 2024.11.8 2 hours Replacement of exposed wires and damaged insulators in the 10 kV Erchivan farm overhead line, pruning of the green mass under the line, pruning of the line Erchivan settlement
7814 Astara 2024.11.26 1 hour Replacement of exposed wires and damaged insulators in the 10 kV Erchivan overhead line, pruning of the green mass under the line, pruning of the line Erchivan settlement, Serak, Shuvi, Vaznash, Siyatuk, Mashkhan villages
7815 Astara 2024.11.22 2 hours Replacement of exposed wires and damaged insulators in the 10 kV Erchivan overhead line, pruning of the green mass under the line, pruning of the line Erchivan settlement, Serak, Shuvi, Vaznash, Siyatuk, Mashkhan villages
7816 Astara 2024.11.12 1 hour Replacement of exposed wires and damaged insulators in the 10 kV Erchivan overhead line, pruning of the green mass under the line, pruning of the line Erchivan settlement, Serak, Shuvi, Vaznash, Siyatuk, Mashkhan villages
7817 Astara 2024.11.4 1 hour Replacement of exposed wires and damaged insulators in the 10 kV Erchivan overhead line, pruning of the green mass under the line, pruning of the line Erchivan settlement, Serak, Shuvi, Vaznash, Siyatuk, Mashkhan villages
7818 Astara 2024.11.27 2 hours Replacement of exposed wires and damaged insulators on the 10 kV Sanjaredi overhead line, pruning of the green mass under the line, pruning of the line Erchivan settlement, Artupa, Sanjaredi Alasha, Shovash, Zungülash, Istisu villages
7819 Astara 2024.11.14 2 hours Replacement of exposed wires and damaged insulators on the 10 kV Sanjaredi overhead line, pruning of the green mass under the line, pruning of the line Erchivan settlement, Artupa, Sanjaredi Alasha, Shovash, Zungülash, Istisu villages
7820 Astara 2024.11.5 2 hours Replacement of exposed wires and damaged insulators on the 10 kV Sanjaredi overhead line, pruning of the green mass under the line, pruning of the line Erchivan settlement, Artupa, Sanjaredi Alasha, Shovash, Zungülash, Istisu villages
7821 Astara 2 hours Reconstruction of the 10/0.4 kV side of the 10 kV Siyaku overhead line Siyaku Executive Representation, Askhanakaran Executive Representation, Hamocham Executive Representation
7822 Astara 2024.11.26 1.5 hours Reconstruction of the 10/0.4 kV side of the 10 kV Siyaku overhead line Siyaku Executive Representation, Askhanakaran Executive Representation, Hamocham Executive Representation
7823 Astara 2024.11.20 2 hours Reconstruction of the 10/0.4 kV side of the 10 kV Siyaku overhead line Siyaku Executive Representation, Askhanakaran Executive Representation, Hamocham Executive Representation
7824 Astara 2024.11.13 1.5 hours Reconstruction of the 10/0.4 kV side of the 10 kV Siyaku overhead line Siyaku Executive Representation, Askhanakaran Executive Representation, Hamocham Executive Representation
7825 Astara 2024.11.5 2 hours Reconstruction of the 10/0.4 kV side of the 10 kV Siyaku overhead line Siyaku Executive Representation, Askhanakaran Executive Representation, Hamocham Executive Representation
7826 Astara 2024.11.1 2 hours Reconstruction of the 10/0.4 kV side of the 10 kV Siyaku overhead line Siyaku Executive Representation, Askhanakaran Executive Representation, Hamocham Executive Representation
7827 Astara 2024.11.27 2 hours Reconstruction work on the 10/0.4 kV side of the 10 kV River factory-3 overhead line Chayoba, Pensar Bala Shahagaci, Qamishli villages
7828 Astara 2024.11.8 1 hour Reconstruction work on the 10/0.4 kV side of the 10 kV River factory-3 overhead line Chayoba, Pensar Bala Shahagaci, Qamishli villages
7829 Astara 2024.11.20 2 hours Reconstruction work on the 10/0.4 kV side of the 10 kV River factory-3 overhead line Chayoba, Pensar Bala Shahagaci, Qamishli villages
7830 Astara 2024.11.1 2 hours Reconstruction work on the 10/0.4 kV side of the 10 kV River factory-3 overhead line Chayoba, Pensar Bala Shahagaci, Qamishli villages
7831 Astara 2024.11.28 2 hours Reconstruction work on the 10/0.4 kV side of the 10 kV Shiyekaran overhead line Pensar, Shiyekaran Kolatan, Shahagaci villages
7832 Astara 2024.11.26 2 hours Reconstruction work on the 10/0.4 kV side of the 10 kV Shiyekaran overhead line Pensar, Shiyekaran Kolatan, Shahagaci villages
7833 Astara 2024.11.21 2 hours Reconstruction work on the 10/0.4 kV side of the 10 kV Shiyekaran overhead line Pensar, Shiyekaran Kolatan, Shahagaci villages
7834 Astara 2024.11.19 1.5 hours Reconstruction work on the 10/0.4 kV side of the 10 kV Shiyekaran overhead line Pensar, Shiyekaran Kolatan, Shahagaci villages
7835 Astara 2 hours Reconstruction work on the 10/0.4 kV side of the 10 kV Shiyekaran overhead line Pensar, Shiyekaran Kolatan, Shahagaci villages
7836 Astara 2024.11.11 2 hours Reconstruction work on the 10/0.4 kV side of the 10 kV Shiyekaran overhead line Pensar, Shiyekaran Kolatan, Shahagaci villages
7837 Astara 2024.11.8 2 hours Reconstruction work on the 10/0.4 kV side of the 10 kV Shiyekaran overhead line Pensar, Shiyekaran Kolatan, Shahagaci villages
7838 Astara 2024.11.6 1.5 hours Reconstruction work on the 10/0.4 kV side of the 10 kV Shiyekaran overhead line Pensar, Shiyekaran Kolatan, Shahagaci villages
7839 Astara 2024.11.4 2 hours Reconstruction work on the 10/0.4 kV side of the 10 kV Shiyekaran overhead line Pensar, Shiyekaran Kolatan, Shahagaci villages
7840 Astara 2024.11.1 2 hours Reconstruction work on the 10/0.4 kV side of the 10 kV Shiyekaran overhead line Pensar, Shiyekaran Kolatan, Shahagaci villages
7841 Astara 2 hours Reconstruction work on the 10 kV side of the 10 kV Leuven overhead line Kijaba Executive Representation, Pelikash Executive Representation
7842 Astara 2024.11.26 1 hour Reconstruction work on the 10 kV side of the 10 kV Leuven overhead line Kijaba Executive Representation, Pelikash Executive Representation
7843 Astara 2024.11.20 2 hours Reconstruction work on the 10 kV side of the 10 kV Leuven overhead line Kijaba Executive Representation, Pelikash Executive Representation
7844 Astara 2024.11.13 2 hours Reconstruction work on the 10 kV side of the 10 kV Leuven overhead line Kijaba Executive Representation, Pelikash Executive Representation
7845 Astara 2024.11.5 1.5 hours Reconstruction work on the 10 kV side of the 10 kV Leuven overhead line Kijaba Executive Representation, Pelikash Executive Representation
7846 Astara 2024.11.1 2 hours Reconstruction work on the 10 kV side of the 10 kV Leuven overhead line Kijaba Executive Representation, Pelikash Executive Representation
7847 Tovuz 2024.11.6 3-4 hours Replacement of 5 unusable wooden supports with metal supports in 10 kV Chatakh h/x Kazimli, Chatakh, Hacilar, Shikheybat, Munjuglu and Gosha villages
7848 Tovuz 2024.11.5-21 3-4 hours Pruning of the green mass under the line at 6 kV II Nizami h/x and trimming of loose wires Part of Tovuz city
7849 Tovuz 2024.11.25 3-4 hours Pruning of the green mass under the line at 10 kV Alakol h/x and pruning of loose wires Alakol village
7850 Tovuz 2024.11.20-25 4-5 hours Replacement of 5 unserviceable supports and damaged insulators in 10 kV Subartesian h/x Abulbeyli and Duz Jirdakhan villages